Measured results, documented closures.

ERG case studies, with the data behind them and a one-page PDF of each for your files or your client. Ongoing and recently closed thermal projects from 2026 will be added as their results become available.

Case study · Electrical resistance heating

Jackson Park NEX Gas Station Leak Area

Source area remediation · NAVFAC Northwest · Bremerton, Washington

The Jackson Park NEX Gas Station Leak Area lies within a CERCLA site near Bremerton, Washington. Gasoline range petroleum hydrocarbons (TPH-G) with appreciable BTEX impacted the upper 55 feet of Vashon Till soil and perched groundwater.

Under contract to Tetra Tech EC, Inc. (TtEC), ERG remediated the source area with continuous electrical resistance heating and periodic dual-phase extraction, partnering with Global Remediation Solutions (GRS) to build and operate the in situ thermal remediation system. GRS was then led by Michael Dodson, Robert D’Anjou and Allen Swift.

Seventy-six electrodes on 15 ft centers in a three phase array treated 21,900 cubic yards to 52 ft below ground surface. The system removed about 19,000 lbs of contaminants of concern and reduced dissolved TPH-G and BTEX concentrations by 99%. The project was completed in 2018.

Panorama of the 76-electrode ERH wellfield at the Jackson Park NEX Gas Station, with surface conveyance piping and power cabling across the treatment area
The 76-electrode ERH wellfield at the Jackson Park NEX Gas Station Leak Area, Bremerton, Washington.
19,000 lbsContaminants removed, vapor and dissolved
21,900 yd³Soil treated in the vadose and saturated zones
99%Reduction in dissolved TPH-G and BTEX
2018Project completed
Electrode layout plan showing three treatment zones at Jackson Park
Electrode layout and treatment zones.
Chart of cumulative contaminant mass removed in the vapor phase, rising to about 18,339 pounds by March 2018
Cumulative contaminant mass removed in the vapor phase, September 2017 to March 2018.
Chart of average contaminant concentrations in groundwater before, during and after ERH, falling by about two orders of magnitude
Average contaminant concentrations in groundwater before, during and after ERH.
Case study · Combined thermal remedy

Carson Plaza

Combined in situ remediation beneath an operating dry cleaner · Carson, California

Soil and groundwater beneath an operating dry cleaner and strip mall were impacted with PCE, TCE, DCE and vinyl chloride to 30 feet below ground surface. Soil at 16 feet reached 860 µg/kg PCE and 1,700 µg/kg TCE, and groundwater hot spots reached 4,600 µg/L PCE and 18,000 µg/L TCE.

The site was remediated in phases while the businesses stayed open. Vapor extraction, dual-phase extraction and limited groundwater extraction came first. Targeted electrical resistance heating then accelerated mass removal, followed by chemical oxidant injection with continued vapor extraction. In the final phase, a focused eight-well HETR™ thermal conduction heating wellfield operated with soil vapor extraction to treat the residual source zone.

Working under a guaranteed performance contract to reach MCLs, the remedy reduced concentrations about 99% across soil, groundwater and soil vapor. After groundwater reached non-detect, oversight transferred from the Los Angeles Regional Water Quality Control Board to DTSC, which issued a No Further Action determination for unrestricted land use on August 24, 2026, the strongest closure outcome available.

~99%Reduction in soil, groundwater and soil vapor
NDGroundwater reached non-detect
Aug 2026DTSC No Further Action
UnrestrictedLand use, including residential
Vapor extraction and treatment equipment at Carson Plaza
Thermal and vapor extraction wellheads at Carson Plaza
HETR wellhead with vapor extraction connection at Carson Plaza
Team experience

Behind every ERG design.

ERG’s team has implemented more than 110 thermal remediation projects worldwide, across every established heating method. These counts include projects completed by ERG team members at prior firms.

ERH · 1995 to 2019

79

Electrical resistance heating projects

TCH · 2016 to present

24

Thermal conduction heating projects: electric, fuel fired and HETR™

SEE · 2000 to 2020

10

Steam enhanced extraction projects

Combined

7

Combined source zone remedies integrating thermal with complementary technologies

Thermal wellfield and vapor conveyance installed inside a warehouse
ERG crew installing conveyance piping in a trench
Drill rigs installing a thermal wellfield
Next step

Have a contaminated site? Let’s engineer the closure.

Send us the basics: contaminants, depth, geology and the cleanup goal. A principal will review the site and tell you whether heat fits, which approach, and what a full evaluation involves.